Client AUSENCO – MINA CONSTANCIA
Location CUSCO – Perú
Date 2013
Flow 225 m3/day y 81m3/day
Load 90 Kg/day de DBO y 32.4 Kg/day of DBO
Solution Domestic Wastewater Plant
Wastewater plant, Constancia camp
Supply of 2 treatment plants for 1,500 and 450 inhabitants, which consisted of aerobic biological treatment of activated sludge with conventional aeration, followed by a disinfection process and for the sludge line, a stage of digestion and thickening is considered.
The system is distributed in 2 treatment lines for the 1,500-inhabitant plant and a single line for the 450-inhabitant plant, followed by a single disinfection stage.
The scope of this project covers the development of detailed engineering and supply of equipment.